What are the two controls needed for a baseline plan?

Prepare for the Cost Controls Exam. Practice with flashcards and multiple-choice questions, each equipped with hints and detailed explanations. Ace your exam!

Multiple Choice

What are the two controls needed for a baseline plan?

Explanation:
A baseline plan is the approved target set for how long the work should take and how much it should cost, used to measure performance. The two controls that matter most are the schedule baseline and the cost (budget) baseline. These give you the reference points for time and money, so you can spot schedule variances and cost variances, track progress, and forecast final completion. Because baselines are commitments, any proposed change goes through formal change control, and only approved changes update the baselines. Other controls like quality checks, safety plans, or a risks-and-issues log are important for different aspects of project governance, but they don’t provide the primary time-and-cost performance reference that a baseline plan relies on.

A baseline plan is the approved target set for how long the work should take and how much it should cost, used to measure performance. The two controls that matter most are the schedule baseline and the cost (budget) baseline. These give you the reference points for time and money, so you can spot schedule variances and cost variances, track progress, and forecast final completion. Because baselines are commitments, any proposed change goes through formal change control, and only approved changes update the baselines. Other controls like quality checks, safety plans, or a risks-and-issues log are important for different aspects of project governance, but they don’t provide the primary time-and-cost performance reference that a baseline plan relies on.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy